Town of Brownsburg updates residents on local traffic projects

The new traffic signal at 56th Street and Wild Ridge Boulevard is expected to be complete August 1. The contractor has installed spans, pedestrian poles for push buttons, wiring, cabinet and signal heads. Pavement markings will be done this week.

Construction of the roundabouts at Hornaday Road and CR 300N and at Northfield Drive and CR 400N are still on track to be complete by July 31. Due to the projects’ accelerated schedules and last week’s extreme heat, the Town gave permission for the contractor to work extended hours.